Qantas expecting additional six-month delay for 787
Thursday October 30, 2008
As the strike by the International Assn. of Machinists and Aerospace Workers appeared to be concluding, Boeing's largest airline customer for the 787, Qantas Group, confirmed that its first Dreamliner could be up to an additional six months late.
Jetstar Airways executives told ATWOnline this week that the LCC's first 787 is not expected until May 2010, 21 months later than the original schedule. A spokesperson added, "Based on what we have been told, we are working on contingencies and planning for a further three-to-six-month delay in our delivery, although Boeing is yet to formally confirm that." The lag is far longer than the 54-day IAM strike and confirms ATWOnline's report last month that there has been further slippage in the program, possibly due to brake control issues.
Jetstar and Qantas have ordered 65 787s, with the original schedule calling for the first 15 to arrive one per month at Jetstar from August 2008. When Boeing announced its third program delay last April, Jetstar's first delivery, ship 21, had slipped 15 months to November 2009.
The manufacturer encountered power supply and brake software problems early this year, and while the power issues were resolved in time for the June power-on goal , the software problems lingered until last month, Boeing insiders say. The brake control monitoring system is supplied by Crane Aerospace to GE Aviation Systems. A GE spokesperson told ATWOnline this month that "there are [now] no outstanding issues," and added last week that the software is "running well. The brake control monitoring system hardware for the test aircraft has been completed as well."
First flight, and thus first delivery, have been complicated and delayed further by the machinist strike. IAM members are scheduled to vote Saturday on the tentative four-year agreement reached Monday evening. If the deal is ratified, workers may return to work as early as Sunday night.
Boeing Chairman, President and CEO Jim McNerney said last week in a teleconference that the 787 was "on schedule" for a fourth-quarter test flight "pre-strike." He said the supply chain "largely healed up" and had caught up before IAM walked out on Sept. 6.
But ongoing production problems have delayed the planned ramp-up as well as first flight and delivery, with some delivery delays stretching to two years. Launch customer ANA confirmed last month that the ambitious production ramp-up schedule will not be achieved. It suggested that its first aircraft would arrive next August, but that now appears to have slipped to early 2010.
by Geoffrey Thomas
ATWOnline
Thursday October 30, 2008
As the strike by the International Assn. of Machinists and Aerospace Workers appeared to be concluding, Boeing's largest airline customer for the 787, Qantas Group, confirmed that its first Dreamliner could be up to an additional six months late.
Jetstar Airways executives told ATWOnline this week that the LCC's first 787 is not expected until May 2010, 21 months later than the original schedule. A spokesperson added, "Based on what we have been told, we are working on contingencies and planning for a further three-to-six-month delay in our delivery, although Boeing is yet to formally confirm that." The lag is far longer than the 54-day IAM strike and confirms ATWOnline's report last month that there has been further slippage in the program, possibly due to brake control issues.
Jetstar and Qantas have ordered 65 787s, with the original schedule calling for the first 15 to arrive one per month at Jetstar from August 2008. When Boeing announced its third program delay last April, Jetstar's first delivery, ship 21, had slipped 15 months to November 2009.
The manufacturer encountered power supply and brake software problems early this year, and while the power issues were resolved in time for the June power-on goal , the software problems lingered until last month, Boeing insiders say. The brake control monitoring system is supplied by Crane Aerospace to GE Aviation Systems. A GE spokesperson told ATWOnline this month that "there are [now] no outstanding issues," and added last week that the software is "running well. The brake control monitoring system hardware for the test aircraft has been completed as well."
First flight, and thus first delivery, have been complicated and delayed further by the machinist strike. IAM members are scheduled to vote Saturday on the tentative four-year agreement reached Monday evening. If the deal is ratified, workers may return to work as early as Sunday night.
Boeing Chairman, President and CEO Jim McNerney said last week in a teleconference that the 787 was "on schedule" for a fourth-quarter test flight "pre-strike." He said the supply chain "largely healed up" and had caught up before IAM walked out on Sept. 6.
But ongoing production problems have delayed the planned ramp-up as well as first flight and delivery, with some delivery delays stretching to two years. Launch customer ANA confirmed last month that the ambitious production ramp-up schedule will not be achieved. It suggested that its first aircraft would arrive next August, but that now appears to have slipped to early 2010.
by Geoffrey Thomas
ATWOnline