Da notizie in lingua spagnola apparse in rete, sembrebbe che riescano a ripararlo e dovrebbe essere pronto per il decollo il prossimo 23 Marzo
Mi auto quoto


ky: Ed Force One Riparato
http://ironmaiden.com/news/article/ed-force-one-repaired
Ed Force One rescue mission summary
From: Magnús Asgeirsson, Air Atlanta
• SATURDAY MARCH 12
Aircraft reported to have had a ground incident
Part sourcing starts
Boeing notified
• SUNDAY MARCH 13
Emergency meeting at Air Atlanta headquarters where a rescue mission plan is set out.
Inspection criteria received from Boeing.
• MONDAY MARCH 14
Inspection in progress
All required parts located
Engines are located in Hannover, Germany
Cowlings and thrust reverser are located in Kemble, UK
Tooling and consumable material in Jeddah, Saudi Arabia
• TUESDAY MARCH 15
Inspection in progress
Charter secured with Cargolux, charter route LUX-STN-SCL. Due to size of the cowlings and
thrust reverser it was decide to have the charter pick them up in Stansted, to save time.
Special road permits would have to be obtained and the truck escorted from Kemble to
Luxemburg. Preparation on getting the engines, cowlings, thrust reverser, tooling and
consumables to LUX and STN starts.
Engines to be trucked Hannover to Luxembourg
Cowlings and thrust reverser to be trucked from Kemble to Stansted
Tooling and consumables to be sent on a flight Jeddah to London Heathrow, then trucked to
Stansted
• WEDNESDAY MARCH 16
Inspection in progress
Engines arrive in LUX
Cowlings and thrust reverser arrive in STN
Due to limited amount of personnel in SCL with experience and license on B747-400, Air
Atlanta decides to send a “Task Force” on site to work around the clock to get Ed Force One
back in the air.
• THURSDAY MARCH 17
Inspection in progress
Tooling and consumables arrives in STN. Charter departs from LUX.
• FRIDAY MARCH 18
Inspection in progress
All parts and equipment arrives in SCL. Engine towed to the LAN Chile Maintenance ramp
and preparation for the engine change started.
• SATURDAY MARCH 19
Inspection in progress
#1 engine replacement completed.
• SUNDAY MARCH 20
Inspections completed, no structural damage to Ed Force One.
#2 engine replacement completed.
• MONDAY MARCH 21
Thrust reverser replaced and cowlings installed.
Leak checks carried out.